Timeline for Milestones
|
|
July 13th, 2006: Meet with
neighbors July
31st, 2006: Meet with Housing
Commission
August 21st, 2006: Meet with Ashland
Parks Commission August 23rd,
2006:
Submit to Ashland Planning
Department |
| |
|
October 25, 2006:
Meet with Conservation Commission
November 9th, 2006: Meet with Tree Commission
November
14th, 2006: Present
to Planning Commission |
|
|
|
July 10, 2007: Present updated plan to Planning
Commission |
| |
|
August 28, 2007: Granted Approval from Planning
Commission |
| |
|
November 20th, 2007:
Granted Approval from City
Council March 26th, 2008:
Gained Approval from Jackson
County |
| |
|
Winter 2008: Work on Final Plan, design homes
June 2008: Interested parties meeting
with design team
Late Summer 2008: Groundbreaking for Phase
I
Spring 2009: Groundbreaking for Phase
II |
|
|
|